Rotary Ash Coolers for 2x235MW Attarat Oil Shale Power Plant, Jordan (SHI FW Boiler)


Release time:

Apr 20,2020

Project Details
Owner: Attarat Power Company
Owner Engineer: Mott Macdonald, UK
EPC Contractor: Guangdong Power Engineering Co., Ltd.
Technical Advisor of EPC Contractor: Worley Parsons, China

Features
◆ 2 x 235MW boiler supplied by SHI FW
◆ 40 x 30t/h ash coolers for bottom ash by Songling
◆ 8 x 6t/h ash coolers for horizontal pass by Songling
◆ Boiler Bottom Ash flow (worst case): 501TPH/per Boiler
◆ Cooling water: condensate water
◆ Design pressure: 3.9Mpa

 

1