Ash Handling System for STANARI 1*300MW CFB Project, Bosnia and Herzegovina


Release time:

Apr 20,2020

Location:

Near the Stanari lignite mine, Bosnia and Herzegovina

Features:
Project: STANARI 1×300MW CFB Power Plant, Bosnia and Herzegovina
EPC Contractor: Dongfang Electric
Fuel: Lignite
PO Effective Date: March, 2012
Scope of Supply: Rotary Ash Coolers, Bucket Conveyor, Bucket Elevator, Bottom Ash Silo, Fly Ash Silo, Bottom Powder Silo, Bed Material Silo
Delivery Date: April, 2014

Design and Fabrication Code: 
◆ ASME, and in compliance with the following EC directives:
◆ Machine Directive 2006/42/EC
◆ Pressure Equipment Directive 97/23/EC
◆ Low Voltage Directive 2006/95/EC
◆ Electromagnetic Compatibility Directive 2004/108/EC

 